Last year, PBJV has managed to get one of EPCC project from PDB. The project called EPCC of Upgrading Bintulu Bunkering Project. The overview of the project is that, they intent to upgrade their bunkering facilities by introducing new pump and pipeline to cater new product called MFO (Marine Fuel Oil) 380. These MFO is use for ship boiler. PBJV appoint me as Project Director & Manager for E&I portion since they strongly believe with my capability to handle such a job. For me it's ok. The project is small scale and the system & sub system also not much to handle. But the tricky is that I have to start with engineering. Meaning I have to start with conceptual design, then go to detail design and finally finally engineering before procurement, installation and commissioning. To make it happen, I have to take good engineer to support me, therefore, with strong recommendation, I bring in 2 engineer to help me. Luckily, these 2 engineer is good and can rely on.

I start to plan and strategize the work. I had talk with several potential partner and finally I found the right one. We work out the contract, the commercial and when everything is in order, we start materialize our project.

Now the project is almost come to end. The commissioning stage just around the conner. I have deliver my promises to my immediate superior, but of course, when we did something good, there must be have a people around us envy with our achievement.

When the year 2009 become very close. I had talk to my management about my intention to quick because in my opinion, I'm no longer qualified to lead this struggle. I'm offer myself to quick. But they have other opinion instead. They want to put me in the new department which I can develop & explore more about other things. I accept the offer to work with expatriate. So far everything is ok. I felt that much comfort and job description is much much clear compare to previous assignment.

As of today, I managed to compete several tender exercise. These are the following project involved :-

i. Transportation & Installation of Inter Platform Pipeline Dragon Tortoise Field – Vietnam Soviet Petroleum.
The project scope of work is Engineering, Construction and provision of As Built Documentation for 25km 8” and 10” pipeline on Dragon and Doi Moi Field which includes 6 nos of Riser, 1 no of expansion spool piece and 1 no of pipeline crossing.


ii. Transportation & Installation of MDD Jacket, Topside and Inter Platform Pipeline – Carigali – PTTEPI Operating Company Sdn. Bhd. (CPOC)
The project scope of work is transportation and installation of MDD Jacket (600MT) & Topside (700MT) c/w Jacket Piles and Appurtenance together with 18” inter platform pipeline.

iii. Transportation & Installation of Substructure & Topside of Kebabangan Northen Hub Development Project – Kebabangan Petroleum Operating Company (KPOC)
The project scope of work is transportation & installation of Offshore Substructure (14,500MT) c/w Jacket Piles, Conductors & Appurtenance together with Topside (18,000MT).